To the central content area

Clean Pigs and Water Quality Improvement Plan of Taitung County

Absrtact
The period of this project is from February 26 to December 31, 2018. The summary of the project are as follows: (1)Counseling the 21 farms management and improvement of the wastewater treatment plant.(2)Analysis the water quality for river, and the farm's sewage treatment plant.(3)Analysis the the results of farms investigations of every months when the period of this project. (4)Find out the farm of the county.(5)Completing of 2 propaganda, 2 observation tour, submitting 1,000 informational materials, and the news release.(6) Promotional assistance the Water pollution control fees expropriation.
Keyword
pig toilet system, clean pig farming, Water quality improvement